A rigging plan is not paperwork. It is the design of the operation.
Many treat the rigging plan as an audit document. It is the engineering work that determines whether the operation is possible at all.
A rigging plan answers questions that admit no guessing: the real weight of the piece and where its centre of gravity sits; the working radius at every point of the slew; which boom and counterweight configuration covers that radius; which rigging gear takes that load at that angle; and what happens if the wind picks up mid-movement.
When the plan is written after the equipment is already booked, it stops being design and becomes justification. The crane already on site becomes the fixed variable and everything else bends around it — which is exactly backwards.
On the Iguatemi arch lift, the piece required a 180° rotation in the air with interference from the crane's own structure. That is found in the plan. Later, with the load in the air, it is no longer information: it is an accident.